On Aug. 29, 2005, Hurricane Katrina struck the Domino Sugar Chalmette Refinery with winds of up to 135 mph. The following is a timeline of the American Sugar Refining plant's remarkable recovery:
- Sept. 16: The first response recover team was onsite.
- Sept. 19: All 326 employees are accounted for.
- Sept. 28: Diesel-generator electrical power is restored.
- Oct. 12: The last trailers arrive.
- Oct. 27: Service water power is restored.
- Nov. 3: Boilers are back online, generating steam.
- Nov. 14: Employees are able to go back to work.
- Dec. 5: Refining operations resume.
- Dec. 9: The first post-Katrina railcar of product is loaded and shipped.